Tripura’s first flyover: Agency facing big challenge in the construction due to land acquisition problem and alleged lack of communication from AMC, Project head talks to TIWN
TIWN
Tripura’s first flyover: Agency facing big challenge in the construction due to land acquisition problem and alleged lack of communication from AMC, Project head talks to TIWN
PHOTO : Flyover construction going on at Agartala. TIWN File Photo.

AGARTALA, March 30 (TIWN): The assigned construction agency NBCC is facing tough time with the drilling work mainly from government press at Bordowali area to Nagerjala due to the land acquisition problem and alleged lack of communication from AMC regarding the under lying water pipes crossing the roads, said construction Project head.

Talking to TIWN correspondent, Flyover construction project head further said that as AMC has not communicated with the construction agency regarding underlying water pipes the workers are facing problem in drilling. Now the biggest problem in front of agency which is creating hurdles in the construction is regarding land acquisition issue mainly from government press at Bordowali area to Nagerjala.

It is to be motioned here that Construction of the first pier is already completed for two pillars and by April 4 the girder for the 39th and 40th pillar at Battala would be ready.

The land acquisition issue at Bordowali and underground water pipe channels are creating problems for the agency to carry out the construction work in the mentioned area. As the government has not yet made clear the underground set up of the underground water channels the construction agency is facing problem to carry out the work smoothly.

It is to be mentioned here that of 68 pillars which would be set up in the entire stretch of the pillar from Dropgate to firebrigade chowmuhani where work for the 28 pillars is underway so far.

The construction of the first pier for most of the pillars is underway.

The work is carried out 24 hours in a day without any break and around 300 labourers are engaged in the work. However, they are guided by about 50 to 52 efficient engineers.

Maintaining the quality of the construction material is the top most priority of the company, effort is made to provide quality work.

With the aim to complete the construction work in the given deadline, flyover work is carried out in full swing.

Iron frame structure for pillars is already set up with the help of steel and iron bars and cement concrete. With the ongoing days, it is seen that the work progress is gaining momentum and will be completed in the given duration.

The construction work of the first ever flyover of Tripura has gained momentum as the work has began in fullswing at all the spots.

Looking forward to complete the fly over construction in the given deadline, the work is progressing in full swing. However, with the completion of the basement work at Battala the work is extended towards bordowali.

The flyover was a long term demand of the city dwellers and it needs to be introduced soon to contain heavy traffic congestion which is increasing along with the moving hands of the clock.

 